CONSTRUCTION UPDATES: It is anticipated that Kimball / Marshall Avenue will re-open in the late afternoon on Friday 12/3/21. Construction will continue through the month of December 2021. During this time, the road may be reduced to one lane to facilitate work. Motorists should expect delays. The recreation path will not be open at this time. The contractor will return in the spring 2022 to finish all remaining work.
Project Description
The purpose of the Muddy Brook Culvert project at Kimball & Marshall Avenue is to: replace the failed culvert and temporary bridge with a permanent crossing structure, provide solutions / treatments that will improve water quality in Muddy Brook, provide safe facilities for all users (including vehicles, pedestrians, and cyclists) to cross Muddy Brook, and improve bicycle and pedestrian connectivity between Williston and South Burlington.
Problem
The existing 15’ diameter corrugated metal pipe culvert was originally constructed in 1986. Due to substantial corrosion the pipe failed in the spring of 2017 causing the closure of Kimball/Marshall Avenue at this crossing until a temporary bridge was installed in August 2017.
During the 2019 “Halloween Storm”, the corrugated metal culvert washed out completely. Damage from the storm required that the temporary bridge be closed. Work was completed to stabilize the area and re-open the bridge, but a permanent stream crossing needs to be installed.
Timeline
After the culvert washed out in October 2019 the City worked quickly to obtain emergency funding to stabilize the area so that the temporary bridge could be reopened. The City then accelerated the engineering design schedule and obtained grants to allow for a replacement culvert to be installed as soon as possible.
The current schedule anticipates that construction will begin on Monday August 2, 2021. Kimball and Marshall Avenue will be closed starting on Monday August 2, 2021 and the temporary bridge will be removed. Substantial completion and reopening of the road is anticipated for late November or early December 2021. The contractor will return in the spring of 2022 to finish up various small tasks and complete final paving.
Funding Sources
This project benefited from multiple grant funding sources. Grants received include the following:
- TA Grant 2019- Awarded $300,000
- Town Highway Structures Grant FY20- Awarded $157,371.30
- Federal Highway Emergency Relief Program- Awarded $410,000
- Transportation Alternatives Program FY20 – Awarded $300,000
- Town Highway Structures Grant FY22 – Awarded $175,000
- Town Highway Structures Grant FY22 – Awarded $175,000
Project Information
Invitation to Bid – Muddy Brook Culvert Replacement Project (723 kb)
Page last updated: 11/16/21